IV Commission procedure:
  1. 1. Action by the Grievance Redressal Officer:
    (i) Within 3 working days of receipt of a consumer grievance, the Grievance Redressal officer shall send an acknowledgement to the consumer. Grievances, which fulfill conditions in Para II above, will be registered and serially numbered, e.g., C/01/0, C/02/0 and so on. A copy of the grievance shall be forwarded under the signature of the Grievance Redressal officer within 5 working days of receipt to the Licensee to offer parawise comments and such other information as may be necessary to dispose of the grievance effectively and adequately.
    (ii) Within 14 working days from the date of receipt, the Licensee shall submit its parawise comments and such other information to the Commission on the grievance, failing which it will be deemed that the Licensee has no comments to offer and a decision shall be taken by the Commission as deemed fit and proper unless the time for such a response is extended in writing by the Commission.
    (iii) The period prescribed for submission of the parawise comments shall not be ordinarily extended unless a specific prayer is made on valid and cogent ground to that effect by the Chief Executive of the Licensee and the Commission approves of the same.
    (iv) On receipt of the parawise comments, the case file shall be processed within 14 working days.
    (v) Should a rejoinder from the Complainant be considered absolutely necessary for a just decision of the Consumer grievance, the same may be obtained under the order of the Commission.
    (vi) The powers of the Commission under the Act and powers for investigation, inquiry, collection of information etc., under Chapter III of the Karnataka Electricity Regulatory Commission (General and Conduct of Proceedings) Regulations 2000 shall be applicable in dealing with the grievances.
    (vii) In case, where the Commission considers it appropriate to undertake and discharge the matter through hearing of the affected parties, procedures as laid down in Chapter II of the Karnataka Electricity Regulatory Commission (General and Conduct of proceedings) Regulations, 2000 shall apply.
    (viii) The Commission will pass an order as deemed fit and proper taking into consideration the grievance, the parawise report and such other information supplied by the Licensee and documents, if any, filed by the parties. The final decision on the grievance shall not be delayed beyond three months from the date of receipt in any event.
    (ix) The order passed under Para (viii) shall be implemented by the Licensee within 15 days of the receipt of the order.
    (x) The Licensee shall report compliance to the Commission within 7 days of implementation of the order.
    (xi) Failure to implement the order of the Commission makes the Licensee liable to action under the Act.

 

<<Prev  Next>>


One Unit saved = Two units generated


About us    Mission Statement     New Connection    ESCOMS     Grievances   Customer Charter

Regulations    Reforms    History   Tenders    Tariff    Statistics    Policies   Important Orders  Feedback


copyrightŪ 2001-2002   All rights reserved