REPLACEMENT OF BURNT OUT METERS
REPLACEMENT OF BURNT OUT METERS
1 The cost of burnt out meter shall be collected either in cash or by crossed cheque and burnt out meter shall be replaced by a good meter immediately without any lapse of time
2 If the meter of required capacity is not readily available, the installation shall be connected on "DIRECT CONNECTION BASIS" and immediate action taken to fix a good meter to the installation with in 3 days.
3 The consumption during the direct connection period shall be computed on prorata basis based on the recorded consumption of the previous month or in the month in which the new meter was fixed.
4 The released burnt meter shall be sent to the Meter testing laboratory of the Licensee. If the meter is burnt out due to mistake of Consumer or fault in the Consumer premises, there shall be no refund of the cost of meter collected by the Licensee and if it is due to the technical reasons like voltage fluctuation etc, attributable to the system constraints, the cost of meter collected by the Licensee shall be adjusted against the future energy charges of the Consumer under intimation to the Consumer.
5 The Engineer of Meter testing laboratory of the Licensee shall send a report to the subdivision office duly recording the test results and remarks regarding refund of cost of the meter collected, to the Consumer.
6 Test results and the remarks of the Executive Engineer of Meter testing laboratory of the Licensee shall be recorded in the revenue ledger.

Next>>


About us    Mission Statement     New Connection    ESCOMS     Grievances   Customer Charter

Regulations    Reforms    History   Tenders    Tariff    Statistics    Policies   Important Orders  Feedback


copyrightŪ 2001-2002   All rights reserved