ELECTRIC SUPPLY AND DISTRIBUTION CODE


 
 
line.gif (861 bytes)

RATING OF THE INSTALLATIONS

(Applicable to LT, HT, EHT installations, other than domestic installations)

FILING OF APPLICATION IN ADVANCE AND POWER SANCTION

1 All LT installations are subject to periodical / surprise rating by the Licensee’s qualified Engineer to verify the correctness of the ratings of the equipments connected, to assess power factor, etc. The Consumer shall provide necessary facilities for carrying out such rating. The result of such rating shall be binding on the Consumer. The Licensee shall rate the installation with an electronic type testing equipment preferably with the facility of the printer attached to it which shall provide an automatic print out giving the test readings, percentage error of the meter, connected load in KW / HP / KVA, time, date, R.R. No. etc.

The rated KVA or KW shall be converted into HP by applying conversion factor and in cases where the rated HP exceeds an integral number of HP after conversion, the fractional HP shall be rounded off to the next higher quarter for the purpose of calculation of monthly charge.

2 The Consumer can also get his installation rated by the Licensee on payment of the specified fee, in case of: -
i Additions and alterations in the connected machinery / equipments in his installation.
ii A dispute, if any, consequent on the rating by the Licensee.
3

The date of effect of rating at Licensee’s instance shall be the meter reading date immediately following the actual date of rating. If the rating is at the Consumer’s instance, the date of effect of rating shall be the meter reading date immediately following the date of payment of the rating fee by the Consumer.

If during the rating, the rated load is higher than the sanctioned load the provisions of Section 42.01(iii) shall apply.

4 The rating shall be conducted in the presence of the Consumer or his authorised representative. The rating report shall be signed by the Consumer or his representative for having witnessed the test and for having received a copy of the same.
5
  • In case of installations provided with MD meters and opted for Demand based Tariff, for purposes of billing, the higher of the sanctioned load or MD recorded shall be considered.
  • In all other cases where M.D. meter is not provided, the connected load or the rated load or the sanctioned load which ever is higher shall be taken for the purpose of billing.

Next>>


About us    Mission Statement     New Connection    ESCOMS     Grievances   Customer Charter

Regulations    Reforms    History   Tenders    Tariff    Statistics    Policies   Important Orders  Feedback


copyrightŪ 2001-2002   All rights reserved