PROCEDURE |
| 1 |
The
application in the prescribed form shall be got registered at the jurisdictional section /
subdivision office of the Licensee on payment of registration cum processing fee along
with the following:
Attested
true copies or Photostat copies of the documents
Interior
wiring completion cum test report and the Interior wiring diagram showing the proposed
location of the meter board, prepared by the Licensed Electrical contractor.
Agreement
on Rs.50/- stamp paper in the standard format for permanent power supply
|
| 2 |
The
applicant shall pay necessary deposits |
| 3 |
The
Licensee should verify the application and the enclosed documents at the time of receipt
of application and should give an acknowledgement after satisfying himself of the
completeness of the application. |
| 4 |
The
Licensee shall service the installation at the earliest however with in one month from the
date of receipt of the contractors completion-cum-test report along with the wiring
diagram in a complete manner provided the installation has been wired up as per the
completion report and wiring diagram (CR&WD). |
| 5 |
At the
time of inspection of the installation, if the Licensee notices any defect with reference
to the CR&WD and finds that the installation is not as per I.E. Rules, he shall inform
the applicant to rectify such defects. |
| 6 |
From the
date of receipt by the Licensee of the applicants compliance report of rectification
of defects, installation shall be serviced with in a period of one week. |
| 7 |
General
procedure for arranging power supply shall be complied with by applicant and Licensee