Procedure applicable for Arranging power supply to LT Industrial and Commercial Power Installations

Procedure

1
  • Application in the prescribed form shall be got registered at the jurisdictional Section / Sub-Division Office of the Licensee on payment of registration cum processing fee
  • Attested true copies or Photostat copies of the documents as applicable shall be furnished along with the application.
2 General procedure for arranging power supply as explained under Section 4.00 shall be complied with by applicant and Licensee wherever applicable.
3 Power of 50 KW (67 HP / 59 KVA) and above will not be sanctioned under this category.

 

Note
Even if the requisitioned load is less than 50 KW (67 HP/ 59 KVA) the Consumer has the option of taking the power supply at high voltage. The minimum C.D. in such cases shall be 25 KVA.

 

4 Licensee shall execute the work after collecting the cost towards service line as per Section 30.06. However in case the applicant opts to carry out the work on self-execution basis, the applicant shall be permitted to carryout the work through class-1 LEC at his cost as per Licensee’s specification and sanctioned estimate after due fulfillment of all the conditions laid down in Section 4.05 (iii) (a to h except f). In such cases the cost towards service line shall not be collected. The applicant has to pay supervision charges at 10% on the cost of estimate excluding employee’s cost and MSD.
5 L.T. Trivector Meter with demand indicator shall be provided at the option of the Consumer to avail "Demand based Tariff". In such cases, fixed charges shall be levied on the basis of the sanctioned load or M.D.recorded which ever is higher irrespective of the connected load as long as the LT Trivector meter is maintained in good working condition and not tampered with. If the recorded M.D. is higher than the sanctioned load, penal charges shall apply.

6

For industrial lay outs developed by KIADB / KSSIDC / KEONICS / OTHERS the entire work of HT / LT lines, Transformers etc shall be carried out on self execution basis by the applicant as per the estimate prepared by the Licensee. Supervision charges at 10% on the cost of estimate excluding employee’s cost and MSD is payable.

Next>>


About us    Mission Statement     New Connection    ESCOMS     Grievances   Customer Charter

Regulations    Reforms    History   Tenders    Tariff    Statistics    Policies   Important Orders  Feedback


copyrightŪ 2001-2002   All rights reserved